A lift plan provides a systematic approach to preparing for a lift. It involves taking the opportunity before the load is in the air to consider all the aspects of the lift. It also helps ensure that a lift is properly managed. For example, a lift plan aims to ensure the following:
The crane is safely deployed and operated.
The lifting crew clearly understands its roles and responsibilities.
The workers, the load, and the surrounding equipment and property are protected during the lift.
A lift plan should be prepared any time a crane is used.
Components of a Lift Plan
Consider the following when developing a lift plan:
The load’s weight, dimensions, distribution, centre of gravity, and lifting points
The lifting equipment and gear, including crane capabilities and rigging details
The lifting crew, including their roles and competencies
The lifting method, including maximum hoist line speed
The path the crane and the load will travel during the lift
Requirements (if any) to erect or dismantle lifting equipment
Communication methods and the need for and position of signallers
Wind speed limitations
A sketch of the lifting zone (showing the position of lifting equipment, crew, and load)
Any other important information (e.g., special precautions such as maximum crane travel speed.)
Planning for Critical Lifts
Before starting a critical lift or a tandem lift moved laterally, the employer must ensure that a written lift plan is prepared. These plans can take days or weeks to prepare. Detailed engineering reviews may be needed to address any unique challenges. More resources may be required to handle the lift once the load is on the hook.
The plan should also include the following:
Safe work procedures or a method statement
Other relevant documents (e.g., load capacity chart, range diagram, rigging method)
Risk assessment documents for engineering control